E0041 E041: Implement emergency and standby power systems.
F

Emergency Generator Maintenance Deficiency

Hartwyck At Oak TreeEdison, New Jersey Survey Completed on 12-20-2024

Summary

The facility failed to maintain its emergency generators in accordance with NFPA 99:2012 Edition, which had the potential to affect all residents. During a documentation review, it was discovered that the generator had not been tested at least once every 36 months under load for a minimum of four continuous hours. Additionally, a maintenance report from August 6, 2024, indicated that the fuel system might need rebuilding, including the injection pump and injectors. A subsequent report on August 7, 2024, highlighted that the generator had over 1000 hours of operation and a history of failures, including an inability to carry load and erratic engine speed, compounded by water in the fuel system. The report recommended repairing or replacing the unit to ensure dependability. During an interview, it was confirmed that the necessary repairs had not been made, and there was no current Memorandum Of Understanding (MOU) for a portable rental generator, although efforts were underway to secure one. Furthermore, an observation on December 20, 2024, revealed that the emergency generator's remote annunciator panel at the nurse's station on floor 2 was not functioning properly. The panel lacked a means to show it was receiving power and was not equipped with a lamp test switch to test the operation of all alarm lamps. These deficiencies were communicated to the facility's representative during the Life Safety Code exit conference.

Plan Of Correction

1. All residents have the potential to be affected by this deficient Life Safety Code. A qualified contractor, NJ Ex Order 26.4(b)(1) was contacted and came to assess the generator on 1/6/25 and will complete the following: - The Maintenance Director contacted NJ Ex Order 26.4(b)(10) and executed a new MOU for a portable rental generator on 1/6/25. Rental generator was installed and operational to begin generator repairs on 1/6/2025. - NJ Ex Order 26.4(b)(1) began work to rebuild the generator fuel pump on 1/6/2025. Work was completed on 2/10/2025. Upon completion of the fuel pump rebuild, NJ Ex Order 26.4(b)(1) will perform a four-hour generator load test. Load test was completed on 2/11/2025. - Upon completion of the fuel pump rebuild, NJ Ex Order 26.4(b)(1) will repair/replace the remote annunciator panel to include a means to show that it is receiving power and a lamp test switch(es) to test the operation of all alarm lamps. This work was completed by NJ Ex Order 26.4(b)(1) on 2/11/2025. 2. NJ Ex Order 26.4(b) has been contracted by the facility to provide the required 4 hour load test of the generator every 36 months. The Maintenance Director added the required 4 hour load test to the generator maintenance schedule and will ensure completion every 36 months. The Maintenance Director will be the designated individual responsible for ensuring a current MOU is in place for a rental generator and will provide evidence of this to the administrator annually. The Maintenance Director added a monthly annunciator panel test to the generator maintenance schedule and ensure completion monthly. 3. The Maintenance Director will review the generator maintenance and inspection reports monthly ongoing to ensure that the required testing was completed timely. The results of this will be submitted to the administrator and to the QAPI committee monthly and to the QA committee quarterly ongoing.

Penalty

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
See other E0041 citations
Deficiency in Emergency Generator Fuel and Power Maintenance Planning
F
E0041 E041: Implement emergency and standby power systems.
Short Summary

The facility did not include a plan in its emergency preparedness policy for maintaining generator power and fuel during emergencies. Staff confirmed there was no documented procedure for ensuring emergency power systems would remain operational or for supplying power if the generator failed, as required by federal regulations and referenced standards.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Provide Emergency Power During Generator Outage
F
E0041 E041: Implement emergency and standby power systems.
Short Summary

During a utility power outage, the facility's emergency generator failed, resulting in a loss of power. When repairs were needed, the generator was shut down for several hours, and the facility did not secure a temporary backup generator as required by policy, leaving the building without emergency power.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Provide Letter of Reliability for Emergency Generator Fuel Supply
F
E0041 E041: Implement emergency and standby power systems.
Short Summary

The facility was unable to produce a letter of reliability for its natural gas emergency generator during a record review, leaving its backup power supply vulnerable to fuel supply issues. This deficiency was confirmed by the maintenance director.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Lack of Emergency Generator Fuel Supply Agreement
C
E0041 E041: Implement emergency and standby power systems.
Short Summary

Surveyors found that the facility did not have a written agreement with a fuel vendor to supply propane for its emergency generator, as required by federal regulations. Staff confirmed that a contract had been proposed but was not yet in place, leaving the emergency power plan incomplete for all residents and smoke compartments.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.

Know what gets cited — and walk into your next survey with full visibility

We process and analyze inspection reports and Plans of Correction using AI to surface insights and trends — so you can improve care quality and stay ahead of compliance risk before your next survey.

Get ready for your next survey

See what surveyors are citing in your state and spot your risk areas before they do.

Monthly Citation Reports

Have you been cited for this tag?

Save hours drafting a compliant Plan of Correction — AI built on real approved POCs.

Plan of Correction Writer

Trusted data from CMS and state health departments

Every citation, penalty and Plan of Correction is sourced from public CMS records (latest release June 24, 2026) and official state health department websites — never guesswork.

Trusted by long-term care providers and associations.

Allegria Senior Living logo
FHCA logo
WeCare Centers logo
Care Rehab logo
An unhandled error has occurred. Reload 🗙