K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
D

Failure to Test Electrical Equipment as per NFPA Standards

Rehab & Healthcare Center Of Cape CoralCape Coral, Florida Survey Completed on 02-11-2025

Summary

The facility failed to test electrical equipment in accordance with NFPA 99 and NFPA 110 standards. During a review of the facility's maintenance and testing documents, it was found that there were no records of main and feeder circuit breaker inspections and exercising. The only available record was a thermal imaging report dated May 13, 2022. This lack of documentation was acknowledged by the Maintenance Director, who had recently started working at the facility and was unsure of the current status of the records. The deficiency could result in a loss of power to the facility, energized equipment fires, or fires resulting from devices failing to perform as designed. This poses a risk to the occupants of the building from electric shock hazards or the loss of power providing life support and life safety features of the facility. The report highlights the importance of exercising these breakers to ensure their reliability in the event of a fault or overload situation, as per NFPA 99 (2012 edition) and NFPA 110 (2010 edition).

Plan Of Correction

3/12/25 **Electrical Systems - Essential Electric System** 1. Main and feeder circuit breaker inspection and exercising was completed. 2. Audit was conducted to ensure all other inspections were completed; any abnormal findings were corrected. 3. A. The facility has placed in TELS system a schedule to do the inspection according to the regulatory guidelines to maintain compliance. B. Maintenance director and maintenance staff educated on K918. 4. Maintenance Director will do monthly audit to ensure facility maintain compliance with its inspection and report findings to QAPI.

Penalty

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
See other K0918 citations
Failure to Perform and Document Annual Main and Feeder Breaker Testing
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility failed to perform and/or document required annual testing and exercising of main and feeder circuit breakers in accordance with NFPA 99 and manufacturer recommendations. During record review, no documentation could be produced to show that the annual breaker exercises had been completed, and the Director of Facilities acknowledged this lack of records. This deficiency relates to the essential electrical system that supports life safety and critical branches during emergencies.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Exercise and Document Main and Feeder Breaker Maintenance per NFPA 99
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility did not have documentation showing that the essential electrical system’s main and feeder circuit breakers were exercised annually in accordance with manufacturer recommendations and NFPA 99 requirements. During record review with the Maintenance Director, no records could be produced to verify that these breakers had been properly exercised, and the Maintenance Director acknowledged this failure. This deficiency was cited as affecting all occupants due to noncompliance with required essential electrical system maintenance and testing standards.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Perform and Document Required Generator Battery Testing
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility failed to perform and document required testing of backup generator batteries in accordance with NFPA 110. During record review, no documentation of generator battery testing was available, and the Maintenance Director acknowledged both the lack of records and a lack of knowledge of the NFPA 110 battery testing requirements. The report notes that this failure could result in loss of power affecting life support and life safety features for occupants.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Maintain Required Generator Battery Testing Documentation
D
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors identified a deficiency when the facility could not provide documentation that backup generator batteries were being tested in accordance with NFPA 110 and NFPA 99 requirements. During record review, no records of generator battery testing were available, and the Maintenance Director confirmed he was unable to locate the requested documentation. This failure concerns the essential electrical system that supports life safety and critical functions during power loss.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Perform Required Generator Battery Conductance Testing for Essential Electrical System
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility failed to maintain its Essential Electrical System (EES) in accordance with NFPA 99 and related standards when record review showed that conductance testing was not performed for 2 of 2 sealed generator batteries over a defined period, and only one generator battery was tested during that time. During an interview, the Maintenance Director acknowledged that required testing had not been completed for both batteries. This lapse in required emergency power system maintenance affected the facility’s single EES and all residents and staff relying on it.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Maintain and Document Required Generator Testing and Safety Features
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility failed to maintain required documentation showing that its three generators were tested monthly and inspected and tested annually in accordance with NFPA 99 and NFPA 110. Despite multiple requests, no records of these tests or inspections were provided. During the facility tour, surveyors also observed that none of the three generators were equipped with remote manual stop buttons, and this was confirmed by the Maintenance Director. This deficient practice had the potential to affect all residents in the facility.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.

Know what gets cited — and walk into your next survey with full visibility

We process and analyze inspection reports and Plans of Correction using AI to surface insights and trends — so you can improve care quality and stay ahead of compliance risk before your next survey.

Get ready for your next survey

See what surveyors are citing in your state and spot your risk areas before they do.

Monthly Citation Reports

Have you been cited for this tag?

Save hours drafting a compliant Plan of Correction — AI built on real approved POCs.

Plan of Correction Writer

Trusted data from CMS and state health departments

Every citation, penalty and Plan of Correction is sourced from public CMS records (latest release June 24, 2026) and official state health department websites — never guesswork.

Trusted by long-term care providers and associations.

Allegria Senior Living logo
FHCA logo
WeCare Centers logo
Care Rehab logo
An unhandled error has occurred. Reload 🗙